December 2021

03 December – Fail Fix Stage

Work has progressed now to the fail fix stage in each chamber; this includes the installation of the network and power infrastructure for our array of sensors. 

Also, we are now finalising the HVAC ducting system which will providing heating and cooling to the chambers. Following the completion of this task we will start to commission the HVAC systems for the central core and the chambers in December-January, with an aim for practical completion in February.